Introduction
The plant and its outbuildings were built in the 1940s-1950s. The main equipment at this plant includes:
 
  • intake structure and its weir
  • open channel
  • powerhouse with turbines, generators and control boards.


Technical Information

Plant scheme run of river
Region Lombardia
Municipality Palazzolo sull’Oglio (BS)
River Oglio
Installed capacity 4.010 kW
Average Flow 35.000 l/s
Head 10,71 m
Turbines 1 vertical Kaplan (Tosi)
Commissioning 1958
Italcementi Acquisition 1958

Back
Palazzolo sull'Oglio today...



Palazzolo sull'Oglio yesterday...



Certifications
Glossary
Hydropower plant
"The operating principle of a hydropower plant is very simple: suitably devised turbines convert the potential energy of water falling from higher elevations downstream through streams, channels, and watercourses, into electric energy. Therefore, hydropower relies primarily on rainwater."

kW kilowatt
l/s Litres per second
m metre
MWh Megawatt hour
m3 cubic metre
a.s.l. above sea level
kVA kilovoltampere
Download certificazioni
Certificazione del Sistema Qualità ISO 9001